Connecting Utilities for a New Build

The house is finished and there is no power. It happens more often than it should, and always for the same reason: connections were treated as the last step instead of an early one.

Electricity: start early, because it is the long one

A permanent CFE connection requires the installation to be complete and compliant, with documentation and, above a certain load, its own transformer and the associated infrastructure — which is a project in itself, not a form. Rural or newly subdivided lots may have no nearby line at all, and extending one is the owner's cost, occasionally a large one. Establish availability and load capacity before buying the land, and file early. Construction runs on a temporary supply, which is normal, but a temporary supply is not a substitute for the permanent one.

Water and drainage

Where a municipal network exists, connection is straightforward and the house stores in a cistern regardless, because supply is not continuous everywhere. Where it does not, the property relies on a well or delivered water, both of which change the design. Drainage is the other half: in most of this region wastewater is treated on the property with a biodigester or a compact plant rather than infiltrated, and that decision belongs in the project from the first drawings because the authority reviews it.

Gas

Most homes use LP gas from a stationary tank on the property, sized to consumption and refilled by a supplier, with underground or surface distribution to the kitchen, heaters and any outdoor kitchen. Natural gas networks exist in parts of the region but are far from universal. Position the tank for delivery access and required clearances at design stage, not once the terrace is finished.

ServiceWhat it involvesCost and timeline
CFE permanent connectionCompliant installation, documentation2 – 8 weeks after filing
Transformer and infrastructureHigher loads or distant linesPer project, can be significant
Water connection and cisternNetwork connection plus storage$45,000 – $140,000 MXN
Wastewater treatmentBiodigester or compact plant$25,000 – $600,000 MXN
LP gas installationTank, distribution, safety$25,000 – $70,000 MXN
Fibre internetWhere available at the address1 – 4 weeks

Internet, which decides whether you can work here

Fibre is available across most of the developed corridor and is genuinely good where it exists; coverage thins outside it, where fixed wireless or satellite fill the gap. If working remotely is part of the plan, verify the service at the specific address before buying — coverage maps are optimistic, and neighbours give better answers than providers. Run conduit and cabling through the house during construction, including the outdoor areas you will actually use.

Costs and timelines

Ranges for a residential property in the Riviera Maya. Electricity is the item that most often delays a handover, which is why we file for it while finishes are still in progress rather than afterwards.

Related pages: Water supply and filtration · Wastewater in karst · Electrical installation · Cost to build a house in Mexico

Frequently Asked Questions

Typically two to eight weeks after filing with a compliant installation. Where a transformer or line extension is needed, considerably longer — which is why availability should be checked before buying the land.

Yes, in practice. Supply is not continuous or at constant pressure everywhere on this coast, so the house stores and pumps regardless of the connection.

Fibre across most of the developed corridor is genuinely good. Outside it, coverage thins. Verify at the specific address before buying, and run conduit during construction.

Most homes use LP gas from a stationary tank, sized to consumption. Position and clearances belong in the design, not in a decision made after the terrace is built.

Planning a project on this coast?

196+ completed projects. Fixed-price contracts. Reply in 2 minutes.

Ask on WhatsApp

For owners buying, building and keeping a home here

Closing on property: process and costs · Where to build: area by area · Build or buy in Playa del Carmen? · Cost to build a house in Mexico · How long a build takes · Concierge construction service · Managing a build from abroad

See the full concierge service →