How Much Does It Cost to Develop an Industrial Park in Mexico? (2026)
Cost of a industrial park in Quintana Roo in 2026: the line items that make the budget, prices by town and what drives the cost. Figures from our own quotes and market prices.
Related: Industrial park development · Cancún · Puerto Morelos · Playa del Carmen · Chetumal · Industrial warehouses
1. Costs in 2026 (Cancún base)
| Item | Cost |
|---|---|
| Park infrastructure per m² of saleable lot (roads, water, sewer, drainage, lighting) | $0–$1,000 |
| Power substation and medium-voltage network | $8M–$30M |
| Warehouse shell for lease, per m² | $6,000–$12,000 |
| Wastewater treatment plant for the park | $3M–$12M |
| 10-hectare park, infrastructure | $45M–$110M |
| First phase: 4 warehouses × 2,500 m² | $65M–$120M |
2. By town
| Town | Factor | 10-hectare park infrastructure |
|---|---|---|
| Cancún | ×1.00 | $45M–$110M |
| Puerto Morelos | ×1.09 | $49.1M–$119.9M |
| Playa del Carmen | ×1.04 | $46.8M–$114.4M |
| Chetumal | ×0.92 | $41.4M–$101.2M |
| Cozumel | ×1.22 | $54.9M–$134.2M |
| Isla Mujeres | ×1.26 | $56.7M–$138.6M |
| Holbox | ×1.30 | $58.5M–$143M |
3. Power decides the tenants
Cold storage, light manufacturing and data rooms need capacity the local grid often does not have. A park with its own substation and medium-voltage network can rent to tenants others turn away, so we size power for the target tenant mix and coordinate the CFE process from the start.
4. Phased for cash flow
Infrastructure is built in phases along the main road; warehouses follow signed leases or a speculative first phase. Standard shells — clear height, docks, slab capacity — lease faster and finance easier.
5. Not included
- Land, VAT and financing
- Design and permits: 6–10% of construction
- Contingency 5–10%