Change Orders and Overruns: Keeping the Final Cost Close to the Contract
On the projects we are asked to rescue, overruns of 20–40% are common, and almost never caused by one big event. They come from small undocumented changes, low allowances and missing scope. This is the system we use to keep the final number within a few percent.
Related: Construction Payment Schedule in Mexico · Obra Negra, Obra Gris, Obra Blanca and Turnkey · IVA · Bitácora de Obra · Construction Handover and Punch List in Mexico
1. Where overruns come from
| Cause | Typical impact |
|---|---|
| Allowances too low for the finishes chosen | 5–15% |
| Owner changes during works (layouts, finishes, extra rooms) | 5–20% |
| Missing scope: connections, walls, landscaping, pool equipment | 3–10% |
| Ground surprises (karst, fill, water table) | 0–10% |
| Exchange rate on imported items | 0–5% |
2. The change-order rule
- No change is executed without a written order with price and time impact signed by the owner.
- Changes are priced from the contract's unit-price list, not negotiated from zero.
- Each change is recorded in the bitácora.
- The running total of approved changes is reported with every valuation.
3. Allowances done right
An allowance (partida a definir) for tile, fixtures or kitchen should be set from a real selection at the level you want, not a generic figure. We show allowances per m² or per unit with examples so you know what the number buys.
4. Contingency
| Project | Contingency we recommend |
|---|---|
| New house on a verified lot | 5–7% |
| Villa with pool, complex design | 7–10% |
| Renovation of an existing building | 10–15% |
| Hotel or commercial fit-out | 8–12% |
Contingency is the owner's money: unused contingency stays with you.
5. Price and currency clauses
Fixed-price contracts should name what is fixed (unit prices, total) and for how long. If the build exceeds 12 months, an escalation clause tied to an index (INPC or construction cost index) is fairer than open "increases". Imported items can be fixed in USD. See contract clauses and the payment schedule.