Change Orders and Overruns: Keeping the Final Cost Close to the Contract

On the projects we are asked to rescue, overruns of 20–40% are common, and almost never caused by one big event. They come from small undocumented changes, low allowances and missing scope. This is the system we use to keep the final number within a few percent.

Permitted foundation works on a Recrea construction site
A Recrea Construction project

Related: Construction Payment Schedule in Mexico · Obra Negra, Obra Gris, Obra Blanca and Turnkey · IVA · Bitácora de Obra · Construction Handover and Punch List in Mexico

1. Where overruns come from

CauseTypical impact
Allowances too low for the finishes chosen5–15%
Owner changes during works (layouts, finishes, extra rooms)5–20%
Missing scope: connections, walls, landscaping, pool equipment3–10%
Ground surprises (karst, fill, water table)0–10%
Exchange rate on imported items0–5%

2. The change-order rule

  • No change is executed without a written order with price and time impact signed by the owner.
  • Changes are priced from the contract's unit-price list, not negotiated from zero.
  • Each change is recorded in the bitácora.
  • The running total of approved changes is reported with every valuation.

3. Allowances done right

An allowance (partida a definir) for tile, fixtures or kitchen should be set from a real selection at the level you want, not a generic figure. We show allowances per m² or per unit with examples so you know what the number buys.

4. Contingency

ProjectContingency we recommend
New house on a verified lot5–7%
Villa with pool, complex design7–10%
Renovation of an existing building10–15%
Hotel or commercial fit-out8–12%

Contingency is the owner's money: unused contingency stays with you.

5. Price and currency clauses

Fixed-price contracts should name what is fixed (unit prices, total) and for how long. If the build exceeds 12 months, an escalation clause tied to an index (INPC or construction cost index) is fairer than open "increases". Imported items can be fixed in USD. See contract clauses and the payment schedule.

FAQ

With a complete design and clear allowances, 3–7%. Above 10% usually means scope was missing or changes were not controlled.

Not under a well-written contract; unsigned changes are the builder's risk.

It gives certainty if the design is complete; with an incomplete design it just moves the argument to change orders.

Ask for an open-book budget, a capped fee and the same change-order rules.

Ready to Start Your Project?

196+ completed projects. Fixed-price contracts. Free quote within 48 hours.

Get Free Quote
1-Year Written Warranty18+ Years196+ ProjectsLicensed & DRO

Worked with us? Leave a Google review

Your review helps other owners decide, and helps us improve.

Write a reviewRead our Google reviews