How to Pay a Builder in Mexico: Deposit, Milestones and Retention

Most disputes we are called in to fix started with a payment schedule that ran ahead of the work. This is the structure we use on our own house and villa contracts in the Riviera Maya, and what we recommend you insist on with any builder. It goes deeper than the payment section of our construction contract guide.

Permitted foundation works on a Recrea construction site
A Recrea Construction project

Related: Obra Negra, Obra Gris, Obra Blanca and Turnkey · IVA · Bitácora de Obra · Construction Handover and Punch List in Mexico · Change Orders and Cost Overruns on a Build in Mexico

1. The deposit

A deposit (anticipo) of 20–30% is normal in Mexico: it pays mobilisation, first materials and long-lead orders. More than 30% without a bond or a clear purchase list is a red flag. On cost-plus or management contracts the deposit is lower (one or two months of projected spend).

2. A typical milestone schedule (house / villa)

Milestone% of contractProof before paying
Deposit at signing20–25%Signed contract, programme, licence filed
Foundations complete10–15%Soil / karst verified, photos, DRO entry in logbook
Structure ground floor + slab10–15%Concrete test results, slab inspection
Upper floors / roof slab10–15%Same as above per level
Shell complete (obra negra) + MEP rough-in10%Pressure tests, conduit and pipe photos before closing walls
Finishes, carpentry, windows10–15%Installed items, not just delivered
Handover5%Punch list closed, as-built drawings
Retention release5%30–90 days after handover, defects fixed

3. Rules that protect you

  • Pay against an estimación (progress valuation) checked on site, never against a date.
  • Never be more than one milestone ahead of the work.
  • Keep a 5–10% retention until defects are closed.
  • Buy expensive equipment (A/C, elevators, imported windows) through a direct order or with the invoice in your name.
  • Every payment against a CFDI invoice.

4. USD or MXN, and paying from abroad

Most materials and labour are priced in pesos; imported items in dollars. A contract in MXN with a list of USD items, or a USD contract with a fixed exchange-rate band, avoids arguments. Payments from abroad go by international wire to the builder's Mexican company account against an invoice; keep the bank confirmations and invoices together, you will need them when you sell.

5. Escrow and third-party control

For larger projects or when you are not in Mexico, a site supervisor who signs off each valuation, or a bank / escrow agent that releases funds against the supervisor's report, adds a cost of 2–4% and removes most of the risk.

FAQ

No. 20–30% is normal; 50% only makes sense for small jobs or custom fabrication.

No. Pay the contractor; they are responsible for wages and IMSS. Paying crews directly can make you the employer.

Only if the contract has an escalation clause with an index; otherwise prices are fixed.

International wire to the builder's company account against a CFDI invoice, ideally after a supervisor approves the valuation.

Ready to Start Your Project?

196+ completed projects. Fixed-price contracts. Free quote within 48 hours.

Get Free Quote
1-Year Written Warranty18+ Years196+ ProjectsLicensed & DRO

Worked with us? Leave a Google review

Your review helps other owners decide, and helps us improve.

Write a reviewRead our Google reviews