Handover and Punch List: What to Test Before You Accept the House

Signing the handover (acta de entrega-recepción) starts the warranty clock and usually releases the last payment. This is the inspection we run on our own houses and villas in the Riviera Maya, and what you should demand from any builder.

Permitted foundation works on a Recrea construction site
A Recrea Construction project

Related: Construction Payment Schedule in Mexico · Obra Negra, Obra Gris, Obra Blanca and Turnkey · IVA · Bitácora de Obra · Change Orders and Cost Overruns on a Build in Mexico

1. Tests before the walk-through

TestHowPass criterion
Roof waterproofingFlood test 24–48 h, or wait for a heavy rainNo moisture on ceilings
Water linesPressure test before and after finishesNo pressure drop in 2–4 h
DrainageRun all fixtures togetherNo backflow or odour
ElectricalBreaker labelling, RCD/GFCI trip, earth testAll circuits identified and tripping
A/CCommissioning per unit, condensate linesDesign temperature, no dripping
PoolLeak test, equipment run, chemistryLevel stable 48 h
Windows and doorsHose test on the windward sideNo water inside

2. The punch list

Walk every room with the builder and record each defect with a photo, location and deadline: chipped tile, paint, silicone, door alignment, grout, scratches on glass. Group it by trade. Normal closing time is 2–4 weeks.

3. Documents you must receive

  • As-built drawings (architecture, structure, MEP).
  • Equipment warranties and manuals (A/C, pumps, water heater, elevator).
  • Copy of the bitácora and the completion notice (aviso de terminación de obra) filed with the municipality.
  • Final CFDI invoices and a paid-up statement.
  • Maintenance plan for waterproofing, wood and salt exposure (see home maintenance costs).

4. Retention and warranties

Keep the 5–10% retention for 30–90 days after handover, until the punch list is closed and the first heavy rain has passed. Beyond the contract warranty, the Civil Code gives the owner remedies for hidden defects (vicios ocultos); structural responsibility of the DRO and builder extends for years after completion.

5. Don't sign if

  • Waterproofing or pressure tests were not done.
  • Utilities are still on temporary construction service.
  • There is no as-built set.
  • The builder asks for the retention before the punch list is closed.

FAQ

Yes, if the house is safe and you record in the handover act which items remain open.

Contract warranties are typically 1 year for finishes and installations and longer for structure and waterproofing; the law adds hidden-defect remedies.

The DRO and owner file it with the municipality; it is needed for some utility contracts and for resale.

If you are not on site, yes: an inspection costs a fraction of one hidden leak.

Ready to Start Your Project?

196+ completed projects. Fixed-price contracts. Free quote within 48 hours.

Get Free Quote
1-Year Written Warranty18+ Years196+ ProjectsLicensed & DRO

Worked with us? Leave a Google review

Your review helps other owners decide, and helps us improve.

Write a reviewRead our Google reviews