Handover and Punch List: What to Test Before You Accept the House
Signing the handover (acta de entrega-recepción) starts the warranty clock and usually releases the last payment. This is the inspection we run on our own houses and villas in the Riviera Maya, and what you should demand from any builder.
Related: Construction Payment Schedule in Mexico · Obra Negra, Obra Gris, Obra Blanca and Turnkey · IVA · Bitácora de Obra · Change Orders and Cost Overruns on a Build in Mexico
1. Tests before the walk-through
| Test | How | Pass criterion |
|---|---|---|
| Roof waterproofing | Flood test 24–48 h, or wait for a heavy rain | No moisture on ceilings |
| Water lines | Pressure test before and after finishes | No pressure drop in 2–4 h |
| Drainage | Run all fixtures together | No backflow or odour |
| Electrical | Breaker labelling, RCD/GFCI trip, earth test | All circuits identified and tripping |
| A/C | Commissioning per unit, condensate lines | Design temperature, no dripping |
| Pool | Leak test, equipment run, chemistry | Level stable 48 h |
| Windows and doors | Hose test on the windward side | No water inside |
2. The punch list
Walk every room with the builder and record each defect with a photo, location and deadline: chipped tile, paint, silicone, door alignment, grout, scratches on glass. Group it by trade. Normal closing time is 2–4 weeks.
3. Documents you must receive
- As-built drawings (architecture, structure, MEP).
- Equipment warranties and manuals (A/C, pumps, water heater, elevator).
- Copy of the bitácora and the completion notice (aviso de terminación de obra) filed with the municipality.
- Final CFDI invoices and a paid-up statement.
- Maintenance plan for waterproofing, wood and salt exposure (see home maintenance costs).
4. Retention and warranties
Keep the 5–10% retention for 30–90 days after handover, until the punch list is closed and the first heavy rain has passed. Beyond the contract warranty, the Civil Code gives the owner remedies for hidden defects (vicios ocultos); structural responsibility of the DRO and builder extends for years after completion.
5. Don't sign if
- Waterproofing or pressure tests were not done.
- Utilities are still on temporary construction service.
- There is no as-built set.
- The builder asks for the retention before the punch list is closed.