Obra Negra, Obra Gris and Turnkey: What You Are Actually Being Quoted
Two quotes for the same house can differ by 40% simply because one is obra gris and the other llave en mano. These Mexican terms are used loosely, so here is what each stage normally includes on a Riviera Maya house in 2026, and how to compare like with like.
Related: Construction Payment Schedule in Mexico · IVA · Bitácora de Obra · Construction Handover and Punch List in Mexico · Change Orders and Cost Overruns on a Build in Mexico
1. The stages
| Stage | Includes | Share of a turnkey budget |
|---|---|---|
| Obra negra (structural shell) | Site prep, foundations, columns, block walls, slabs, stairs, roof slab | 35–45% |
| Obra gris (grey work) | Obra negra + concealed plumbing and electrical, plaster (aplanados), base waterproofing, cistern | 55–65% |
| Obra blanca (finishes) | Floors, tiling, paint, ceilings, bathrooms, doors, windows, fixtures | +25–35% |
| Llave en mano (turnkey) | All of the above + kitchen, closets, A/C, pool, garden, connections, cleaning, handover documents | 100% |
2. Price per m² by stage (2026)
| Finish level | Obra gris (MXN/m²) | Turnkey (MXN/m²) |
|---|---|---|
| Standard | $9,000–$11,500 | $15,000–$19,000 |
| Residential+ | $11,500–$15,000 | $20,000–$26,000 |
| Premium | $15,000–$19,000 | $27,000–$35,000 |
| Luxury | $19,000–$28,000 | $38,000–$60,000+ |
Turnkey ranges from our price per m² guide; grey-work share estimated. Pool, land and design fees extra.
3. Where quotes hide the difference
- Windows and doors: often excluded from obra gris but they are 6–10% of the budget.
- A/C: rough-in only vs equipment installed.
- Kitchen and closets: "by owner" in many quotes.
- Allowances (partidas a definir) that are too low for the finishes you want.
- Connections, licences and DRO fees.
4. When obra gris makes sense
Buying a condo or house in obra gris lets you choose finishes, but you take on the coordination and the risk that hidden installations were done badly. Ask for pressure tests and photos of pipes before walls were plastered. For new builds we usually recommend turnkey with clear allowances, see turnkey construction.
5. Comparing two quotes
Put both into the same stage table above, line by line, then check quantities (m² of slab, m² of tile) rather than totals. Our guide to the itemised budget (ES) shows the full structure.